Skip to main content

First Floor Piers

August 11, 2022

Construction crews have been busy installing the first floor piers and preparing the southwest corner of the site for the pouring of the concrete foundation.

July 2022 Time-Lapse Video

August 1, 2022

View the progress made on the New Frontiers construction site for the month of July 2022. Highlights include the installation of the crane as well as some of the first floor building columns.

Crane Installation

July 12, 2022

The crane was delivered in pieces to the New Frontiers construction site and was erected in a day. One of the largest to be used in the Stillwater area, the crane is 143 feet tall and 265 feet long. It will be utilized for 1-1.5 years.

June 2022 Time-Lapse Video

June 30, 2022

The New Frontiers construction site is booming with activity as crews are rapidly drilling the almost 200 piers that will extend down 50 feet to support the building. They also installed the base of the tower crane with 150 tons of concrete in preparation for the remainder of the crane in July.

Crane Foundation

June 15, 2022

Construction crews completed the base of the tower crane by pouring 150 tons of concrete that will cure for two weeks. The remainder of the crane is expected to arrive in several pieces the beginning of July.

Drilling Rigs

June 6, 2022

Drilling rigs are being utilized to dig the specified depth for the New Frontiers building’s piers. The piers are reinforced concrete columns transferring the building’s loads to suitable bearing strata.

May 2022 Time-lapse Video

June 1, 2022

Construction is beginning to ramp up with the finalization of bids and the approved financing by the Oklahoma A&M Board of Regents for an extra $15.2 million to support New Frontiers. This action enabled continued progress on the construction site while protecting against any further market inflation.

Small Crane Added to Construction Site

May 10, 2022

A small crane has been added to the construction site to prepare for the addition of a larger crane next month. It will be one of the largest cranes that has been used in this area and will be prominently seen from across Stillwater.

New Frontiers Construction Headquarters

May 5, 2022

With the completion of the demolition and cleanup of the 4-H Building, a triple-wide construction trailer has been moved to that site and will serve as the New Frontiers construction headquarters and holding area for materials and equipment.

Kayleen Ferguson Site Visit

April 27, 2022

New Frontiers Cornerstone Donor Kayleen Ferguson visited the construction site to see the progress made on the new state-of-the-art facility for OSU Agriculture. Kayleen and Larry Ferguson's historic gift from the Ferguson Family Foundation launched the New Frontiers fundraising campaign and renamed the College.

Groundbreaking Anniversary and Construction Annual Report

April 23, 2022

One year ago, OSU Agriculture celebrated the groundbreaking for the New Frontiers Agricultural Hall. Since that day on April 23, 2021, we have made progress on the construction site. Learn more about the activities during the past year in a video from Dr. Coon included in the New Frontiers Construction Annual Report.

Site Tour for Engineers

April 1, 2022

Dr. Randy Raper, assistant vice president of OSU Agriculture, gave members of the Oklahoma Section of the American Society of Agricultural and Biological Engineers a tour of the construction site during their annual meeting.

March 2022 Time-Lapse Video

March 31, 2022

Construction crews continue to work on underground utilities in preparation for the next phase of construction. The most recent progress was the installation and connection of the chilled water line.

Chilled Water Line Connection

March 16, 2022

Construction crews completed the installation of the chilled water line by connecting and burying the line.

Chilled Water Line Installation

March 2, 2022

Construction crews continue utility work to prepare for the next phase of construction, including the installation of a chilled water line.

4-H Building Demolition and Cleanup Continues

February 15, 2022

As the bidding process winds down and quotes are selected to gear up activity on the construction site, progress is being made on the demolition and cleanup of the 4-H building. Once completed, this site will serve as the construction headquarters for the New Frontiers project.

New Frontiers Sustainability Coverage on KOCO News 5

February 1, 2022

KOCO News 5 in Oklahoma City caught wind of our sustainability plans for the New Frontiers Agricultural Hall and ran a story. The segment featured Dr. Randy Raper, assistant vice president of facilities for Ag Research, and the sustainability plan developed by two former OSU environmental science students for the new building.

New Frontiers Video Update

January 14, 2022

OSU Agriculture celebrates the two-year anniversary of the historic gift announcement by Kayleen and Larry Ferguson that renamed the college and launched the New Frontiers public campaign. Dr. Thomas G. Coon, vice president and dean for OSU Agriculture, highlights the progress made during the past two years.

December 2021 Time-Lapse Video

January 3, 2022

Activity on the construction site was a little slower this month with the holidays. However, crews finished up final utility work for the next phase of construction in the new year.

4-H Building Demolition

December 13, 2021

Demolition of the 4-H building is underway and will continue through January 2022. This site, located at the corner of Hall of Fame and Monroe avenues, will serve as the construction headquarters for New Frontiers Agricultural Hall. Oklahoma 4-H will have a new home in the state-of-the-art teaching, research and Extension facility.

November 2021 Time-Lapse Video

December 1, 2021

OSU Agriculture gives thanks for the progress made on the New Frontiers construction site. The highlight during the November 2021 time-lapse video was the installation of a domestic water line.

Domestic Water Line Installation

November 16, 2021

Slow and steady progress continues on the construction site for the New Frontiers project. Construction crews proceed with utility work, including erosion control and installing a domestic water line.

October 2021 Time-Lapse Video

November 1, 2021

Utility work continues on the construction site for the new home for OSU Agriculture. Check out the time-lapse video from October 2021 to view the progress.

Site Tour

October 20, 2021

A group of OSU faculty and staff, along with members of FlintCo Construction took a tour of the construction site. You don’t realize how big the area is until you are standing in the middle of the construction site with a 360-degree view.

September 2021 Time-Lapse Video

September 30, 2021

The September 2021 time-lapse video from the New Frontiers construction site features more ground work, including covering the many truckloads of fill dumped on the site with gravel that was recycled from the parking lot concrete removed in May 2021.

Site Walk

September 16, 2021

The footprint of the New Frontiers Agricultural Hall is taking shape as construction crews laid gravel, recycled from the concrete of the parking lot that was removed, on top of the many truckloads of fill dumped on the building site. A group walked the site to see progress made and discuss the next phase of construction.

August 2021 Time-Lapse Video

August 31, 2021

Groundwork continues on the construction site of the New Frontiers Agricultural Hall. View the August 2021 time-lapse video to see the many truckloads of fill being brought in to prepare the site for the building pad and foundation.

Dirtwork

August 24, 2021

Construction crews continue to bring in truckloads of fill to prepare the site for the building pad and foundation.

July 2021 Time-Lapse Video

July 30, 2021

Progress continues on the New Frontiers Agricultural Hall for OSU Agriculture. Check out the July 2021 time-lapse video to see the groundwork in preparation for the building pad and foundation.

Groundwork

July 22, 2021

Progress continues on the construction site as crews conduct groundwork in preparation for the building pad and foundation.

June 2021 Time-Lapse Video

June 30, 2021

Construction continues on the New Frontiers Agricultural Hall – the new home for OSU Agriculture. Check out the progress made during June 2021 on the removal of the parking lot and demolition of Agriculture North.

Agriculture North Demolition

June 18, 2021

The sounds on campus along Monroe St. are getting noisier as construction continues and site preparations are made to build the New Frontiers Agricultural Hall. The demolition of Agriculture North is making room for the new home for OSU Agriculture.

May 2021 Time-lapse Video

May 31, 2021

Progress has been made during May 2021 to clear the parking lot to make room for the footprint of the new, state-of-the-art teaching, research and Extension facility.

Parking Lot Demolition

May 21, 2021

Construction has begun on the new home for OSU Agriculture. In May 2021, the parking lot was removed to make room for the footprint of the New Frontiers Agricultural Hall.

Back To Top
SVG directory not found.
MENUCLOSE