May 2023 Building Site Progress

Wednesday, May 10, 2023

The structure and framework are completed in the New Frontiers Agricultural Hall. The roof is expected to be completed in the next 2-3 weeks. Progress also continues on the placement of windows. Workers started on the south end and are moving counterclockwise around the building.

 

North end of the building

 

Work on the chimney on the north side of the New Frontiers building

 

View of the middle section of the New Frontiers building

 

View of the south side of the New Frontiers building